Question: If the project has a negative cost variance, then a. correction actions should be taken on activities that are near-term and have large estimated costs.
If the project has a negative cost variance, then a. correction actions should be taken on activities that are near-term and have large estimated costs. b. more money needs to be expended on the project c. the project should be watched to be sure the project progresses. d. no action is needed to be taken, the project is performing well