Question: Project Management: PERT/CPM: Activity Activity Description Immediate Predecessor (s) Activity Time-Weeks A Define Building Requirements - 7 B Prepare Architectural Drawings - 4 C Refine
- Project Management: PERT/CPM:
| Activity | Activity Description | Immediate Predecessor (s) | Activity Time-Weeks |
| A | Define Building Requirements | - | 7 |
| B | Prepare Architectural Drawings | - | 4 |
| C | Refine Office Layout | B | 6 |
| D | Select Contractor | A, B | 3 |
| E | Prepare/Obtain Building Permits | B | 1 |
| F | Construct Building | D, E | 16 |
| G | Finalize Seating Plan with Tenant | A, B | 4 |
| H | Complete Final Check List Items | F | 12 |
| I | Hold Press Conference | H | 2 |
| J | Plan/Conduct Opening Ceremony | I | 1 |
| K | Tenants Take Occupancy of Building | J | 2 |
Draw the PERT/CPM chart longhand and show the critical path for the project above. You can develop and check your answers using a computer or software package. Attach additional print out sheets if necessary.
- Using the PERT/CPM chart that displays activities, activity times, and activity predecessors for a construction project answer the following questions:
- What is the critical path for the construction project?
- What is the total time for the construction project?
- What would you advise the project manager to do?
- If the architect is delayed in preparing the drawings for the project in activity B by an additional 4 weeks (activity time of B changes from 4 to 8 weeks):
- What is the critical path for the construction project?
- What is the total time for the construction project?
- What would you advise the project manager to do?
- In addition to the delay in B) above, if the local authority closes the permit office due to a furlough and the granting of permits goes from 1 week to 10 weeks:
- What is the critical path for the construction project?
- What is the total time for the construction project?
- What would you advise the project manager to do?