Question: Project Management Q5: A. For the following Table: (10 Marks) Activities Preceded by A T. TO Sd V ES LF T. C.P Tm 6 Tp

Project Management Q5: A. For the following

Project Management

Q5: A. For the following Table: (10 Marks) Activities Preceded by A T. TO Sd V ES LF T. C.P Tm 6 Tp 7 5 B 1 3 5 1 4 7 D A 1 2 3 E B 1 2 9 F 1 5 9 G 2 2 8 H 4 10 E, F D 2 8 8 4 5 HG 2 2 Construct the project network using PERT and find the critical path, expected project completion time and variance for each activity. What is the probability of completing the project on or before 22 weeks? B. What is planning of the material requirements? draw the main block diagram of MPR system. (10 Marks)