Question: This question is about (project management) please. Q2: For the following Table: (25 Marks) Preceded by Te Sd V ES LF T. Activities A C.P

This question is about (project management) please.
Q2: For the following Table: (25 Marks) Preceded by Te Sd V ES LF T. Activities A C.P T. 5 Tm 6 Tp 7 B 1 w 5 1 4 7 D 1 2 3 E B 1 2 9 F 1 5 9 G 2 2 8 H E, F 4 4 10 D 2 5 8 HG 2 2 8 Construct the project network using PERT and find the critical path, expected project completion time and variance for each activity. What is the probability of completing the project on or before 23 weeksStep by Step Solution