Question: Project Management Question 1. The IBM faculty are working on a 12-month, 1 million dollar project to build a parking garage. After 6 months the
Project Management Question
1. The IBM faculty are working on a 12-month, 1 million dollar project to build a parking garage. After 6 months the project status is as follows: PV=$689,500, AC=$750,000, EV=$700,000
(a)What are the Cost Variance, Schedule Variance, Cost Performance Index and Schedule Performance Index?
(b) How is the project progressing schedule-wise and budget-wise?
(c) How long will it take to complete the project? How much will it cost?
(d) Sketch the Earned Value Chart for this project assuming that PV, AC and EV are straight lines.