Question: Project Management question) Create the project network diagram and the GANTT Chart. Calculate the early, late, and slack times for each activity. Identify the critical
Project Management question) Create the project network diagram and the GANTT Chart. Calculate the early, late, and slack times for each activity. Identify the critical path.
NOTE Lag in these problems is represented in the form (PredecessorID)-(LagType) + (LagTime). Eg. B-fs + 5 means task ID B is the predecessor and has a finish-to-start relationship with a lag of 5 time units to the current task ID. fs = finish to start sf = start to finish ff = finish to finish ss = start to start

Create the project network diagram. Calculate the early, late, and slack times for each activity. Identify the critical path. Predecessor(s) ID A B D Duration 5 10 15 5 E 20 A B-fs + 5 C-sf + 20 B Duff + 25 D E-ff + 0 C-fs + 10 F G-ff + 10 F 15 G H 10 20
Step by Step Solution
There are 3 Steps involved in it