Question: Project Management - Risk: ( 6 0 ) Problem 5 : Part 1 - Schedule Risk ( 3 0 ) Given: Consider the following project
Project ManagementRisk:
Problem : Part Schedule Risk
Given: Consider the following project activities, relationships, and probable durations given in the following table.
tableActivitytableImmediatePredecessortableOptimisticDurationdaysatableMost probableDuration daysmtablePessimisticDurationdaysbABACADBEBCFCGDEFHDEIFGH
Using PERT scheduling techniques, determine the following:
A Project Activity Network Diagram.
B Expected Duration of the project
days. Critical path activities
C Probability that the project will be completed in days or less days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
