Question: Project Management Sample Problems IN CLASS Problem 1: A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic

Project Management Sample Problems IN CLASS
Project Management Sample Problems IN CLASS Problem 1: A network consists of the following list. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic Draw the network diagram. Calculate the expected duration and variance of each activity. Calculate the expected duration and variance of the critical path. P-F'P'P Calculate the probability that the project will be completed in less than 28 weeks