Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Probable Pessimistic Expected Variance Time Time
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
| Activity | Preceding | Optimistic | Probable | Pessimistic | Expected | Variance |
| Time | Time | Time | Time | |||
| A | -- | 7 | 9 | 14 | 1.361 | |
| B | A | 2 | 2 | 8 | 0 | |
| C | A | 8 | 12 | 16 | 0 | |
| D | A | 3 | 5 | 10 | 1.361 | |
| E | B | 4 | 6 | 8 | 0 | |
| F | B | 6 | 8 | 10 | 0 | |
| G | C, F | 2 | 3 | 4 | 0 | |
| H | D | 2 | 2 | 8 | 1 | |
| I | H | 6 | 8 | 16 | 2.778 | |
| J | G, I | 4 | 6 | 14 | 2.778 | |
| K | E, J | 2 | 2 | 5 | 0.25 |
| a. | Draw the network diagram. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above |
| b. | Which activities form the critical path? |
| c. | What is the estimated time of the critical path? |
| d. | What are the project variance and the project standard deviation? |
| e. | What is the probability of completion of the project after week 40? |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock