Question: Project Management - The Project Network House Building Project Data Number Activity Predecessor Duration(Month) 1 Design house and obtain financing -- 3 month 2 Lay
Project Management - The Project Network House Building Project Data
| Number | Activity | Predecessor | Duration(Month) |
| 1 | Design house and obtain financing | -- | 3 month |
| 2 | Lay foundation | 1 | 2 month |
| 3 | Order and receive materials | 1 | 1 month |
| 4 | Build House | 2,3 | 3 month |
| 5 | Select paint | 2,3 | 1 month |
| 6 | Select Carpet | 5 | 1 month |
| 7 | Finish Work | 4,6 | 1 month |
-
Create a precedence map of the project on LucidCharts or Google Slides
-
Calculate the backwards and forwards pass
-
Identify the critical path