Question: project management You are a project manager for a construction project. The project is being terminated early. Your team is documenting the level and extent

project management
project management You are a project manager for a construction project. The

You are a project manager for a construction project. The project is being terminated early. Your team is documenting the level and extent of completion of the project. Which of the following processes are you working on? Define Scope Validate Scope C Manage Communications D Control Scope