Question: project manager relies on two teams for software development tasks. From past projects, he has observed that Team X is available 4 0 % of

project manager relies on two teams for software development tasks. From
past projects, he has observed that Team X is available 40% of the time to take on the work, while
Team Y is available 60% of the time. Moreover, the manager has been able to assign tasks to at
least one of these teams 70% of the time
What is the probability that both teams will be available to take on the next project?