Question: Project managers and teams should consider risks and include them in the project charter for all the following reasons EXCEPT: a . the sponsor and

Project managers and teams should consider risks and include them in the project charter for all the following reasons EXCEPT:
a.
the sponsor and core team should be aware of what could prevent them from successfully completing the project.
b.
all project risks should be eliminated before the project charter is signed.
c.
risks that may have a positive impact on the project create opportunities and should be capitalized upon.
d.
risks that may have a negative impact on project objectives should be identified and addressed.