Question: Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods can be used to
Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods can be used to reduce work overloads EXCEPT:
a Require
b Split an activity into two activities and delay the second part.
c Reorder activities when logically feasible.
a Require all prod. Reassign certain activities to other workers.