Question: oject managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods represent a potentially viable
oject managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT:
| Require all project resources to work overtime | ||
| Split an activity into two activities and delay the second part. | ||
| Reorder activities when logically feasible. | ||
| Reassign certain activities to other workers. |