Question: Project managers should follow which three best practices when assigning tasks to complete milestones? Select all that apply. 1 point Balance the workload of tasks
Project managers should follow which three best practices when assigning tasks to complete milestones? Select all that apply. 1 point Balance the workload of tasks between teammates. Consider teammates' familiarity with the tasks. Add an assignee and due date to each task. Assign deadlines to tasks, but not milestones