Question: Project Network Analysis Problem: For the following Project information, find the Slack for Activities B, C, D, and E. Match the correct answers from the

Project Network Analysis Problem: For the
Project Network Analysis Problem: For the following Project information, find the Slack for Activities B, C, D, and E. Match the correct answers from the options provided. ACTIVITY IMMEDIATE PREDECESSOR DURATION (days) 2 A B 3 IA 3 D 4 E A 7 F C D BF E, F, G G . 5 6 Slack for B > [Choose ] Slack for C - [Choose ] Jack for D - [Choose ] > ack for E- > [ Choose + Previous Next