Question: Question 53 Project Network Analysis Problem. For the following Project information, find the Slack tor Activities B,C,D, and E. Match the comme answers from the
Question 53 Project Network Analysis Problem. For the following Project information, find the Slack tor Activities B,C,D, and E. Match the comme answers from the options provided. ACTIVITY IMMEDIATE PREDECESSOR DURATION (day) 2 A 3 . 4 B 3 C D 5 A 5 E C.D 7 6 B.F G E,F,G H Choose! Choose) Slack for B - Choose) Slack for C [Choose) Slack for D- Previous Slack for E- MacBook Air
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts