Question: Project Plan MA 1 2 3 4 MJ S 0 N WBS Activity Percent Budget No. Description Complete Amount D 5 16 7 8 9


Project Plan MA 1 2 3 4 MJ S 0 N WBS Activity Percent Budget No. Description Complete Amount D 5 16 7 8 9 10 11 12 1 Research 100 $10,000 2 Planning 50 20,000 3 Design 100 10,000 5 Prototype 25 20,000 6 Procurement 0 20,000 7 Installation 0 20,000 8 Testing 0 10,000 9 Training 0 50,000 1. What is the total planned duration of the project in months? a.8, b.11, C.30, d. cannot be determined, e. 15 2. What is the total actual cost of the project as of June 1? a.$35,000, b.$45,000, C.$60,000, d.$160,000, e. Cannot be determined with the information provided. 3. What is the total planned value that the project should have earned as of June 1? a $35,000, b.545,000, C.$60,000, d.$160,000, e. Cannot be determined with the information provided. 4. What is the total earned value of the project as of June 1? a $35,000, b.$45,000, C.$60,000, d.$160,000, e Cannot be determined with the information provided. 5. What was the total baseline budget? a $35,000, b.$45,000, C.$60,000, d.$160,000, e. Cannot be determined with the information provided. 6. What was the cost variance for the project as of June 1? a $-10,000, b.$0, c.$10,000, d.$15,000, e.Cannot be determined with the information provided. 7. What was the schedule variance for the project as of June 1? a $-10,000, b.$0, C.$10,000, d.$15,000, e. Cannot be determined with the information provided. 8. Which of the following best describes the project status as of June 1? a. There is an issue that costs are more than expected, b.There is an issue that tasks are being done slower than expected, C. There are no apparent issues with costs or schedules, d. Both a and b, e.Cannot be determined with the information provided. 9. What is the BAC of the project? a $140,000, b.$160,000 C.$130,000, d. $150,000, e. Cannot be determined with the information provided 10. Based the performance as of June 1, what is the EAC? a. 160,000 b. 150,000 c.140,000 d. 130,000 e.Cannot be determined with the information provided