Question: Project precedence relationships, activity durations, and network diagram are shown below. Duration Activity Predecessors (days) B 5 C 4 E B,C 9 H B,C

Project precedence relationships, activity durations, and network diagram are shown below. Duration

Project precedence relationships, activity durations, and network diagram are shown below. Duration Activity Predecessors (days) B 5 C 4 E B,C 9 H B,C 6 ' E,H 3 The critical path is BHI O CHI CEI BEI