Question: Given is a CPM project network diagram as shown below.Network Diagram.png Activity Start A B C D E F G H End day 0 3

Given is a CPM project network diagram as shown below.Network Diagram.png Activity Start A B C D E F G H End day 0336564250 a) The Project Completion time = Blank 1 days.b) The Earliest Start time, ES, of Activity G = Blank 2 days.c) The Latest Finish time, LF, of Activity C = Blank 3 days.d) The critical activities are = Blank 4(ex. Fill in the answer as: ABCD)