Question: Project : Project-H Introduction: This is our first project as a team probably many more to come. Our project is to build a house. Project

Project :

Project-H Introduction: This is our first project as a team probably many more to come. Our project is to build a house. Project / Goal / Scope of work: Our team decided to undertake a project to build a house with 5 beds, and 5 baths with a 5500 sqft area. The owner decided to have the below amenities in-house.

Amenities need to equip: 1.Private swimming pool with climate control. 2.2000 Sqft Lounge with a garden. 3.Conference room with a capacity of 20 people. Cost: Client has 4 million budget and leverage of 250K more in case of extended modifications. This amount includes Land and construction. Time: Client gave us 1.25 years to complete the entire house with all included. Place: Client has the requirement of being the house to be built in Richmond only.

House project Work breakdown structure (WBS) for building a 5,500 sq ft house, including estimated durations for each task: Project Deliverable: Complete House

1.1Sub-Deliverable: Design and Planning

1.1.1 Task: Architectural Design (30 days) 1.1.2 Task: Structural Engineering (20 days) 1.1.3 Task: Building Permits and Approvals (45 days) 1.2 Sub-Deliverable: Site Preparation 1.2.1 Task: Land Clearing (7 days) 1.2.2 Task: Excavation and Grading (14 days) 1.2.3 Task: Utility Connections (10 days) 1.2.4 Task: Foundation Design and Excavation (21 days) 1.3 Sub-Deliverable: Construction 1.3.1 Task: Framing and Roofing (40 days) 1.3.2 Task: Exterior Finishes (30 days) 1.3.3 Task: Interior Walls and Partitions (15 days) 1.3.4 Task: Plumbing and Electrical Systems Installation (30 days) 1.3.5 Task: HVAC Installation (20 days) 1.3.6 Task: Insulation and Soundproofing (10 days) 1.3.7 Task: Flooring Installation (15 days) 1.3.8 Task: Interior Finishes (25 days) 1.3.9 Task: Cabinetry and Countertop Installation (20 days) 1.3.10 Task: Fixture and Appliance Installation (10 days)

1.4 Sub-Deliverable: Exterior 1.4.1 Task: Landscaping and Outdoor Amenities (20 days) 1.4.2 Task: Driveway and Walkway Construction (14 days) 1.4.3 Task: Fencing and Gate Installation (10 days) 1.4.4 Task: Exterior Lighting Installation (7 days) 1.5 Sub-Deliverable: Finalization and Inspection 1.5.1 Task: Final Touches and Clean-up (10 days) 1.5.2 Task: Quality Assurance and Inspection (15 days) 1.5.3 Task: Final Building Code Compliance Check (5 days) 1.5.4 Task: Obtaining Occupancy Permit (30 days) 1.6 Sub-Deliverable: Project Closeout 1.6.1 Task: Documentation and Record Keeping (5 days) 1.6.2 Task: Warranty and Maintenance Information (5 days) 1.6.3 Task: Final Financial Review and Closure (10 days) Please note that the durations provided are rough estimates and can vary based on factors such as project complexity, availability of resources, and external dependencies.

Question :

  • Identify the risk associated with your project, each deliverable and each task. Do not add more than 2 risk events for the tasks.
  • Determine the probability of occurrence
  • The impact of each risk and the difficulty in detection
  • Link the work breakdown structure to the risk breakdown structure term in terms of all the factors including Technicalities, Organizational Risk, Customer Risk ,Project Management Risk, Try to connect them.
  • Have a plan B for each risk event

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!