Question: Project RED are assigned to a company where it needs to be completed in 10 months, and the project's budget is 150,000 USD. 5 months
Project RED are assigned to a company where it needs to be completed in 10 months, and the project's budget is 150,000 USD. 5 months have passed, and 80,000 USD has been used in this project. Upon closer review, 70% of the work for this project has been completed What is the Cost Performance Index (CPI)