Question: QUESTION 3 ( 2 5 Marks ) a ) Pressure from Carren and her Union delegation could potentially generate change resulting in increased complexity of
QUESTION Marks
a Pressure from Carren and her Union delegation could potentially generate change resulting in
increased complexity of the management task, which could lead to jeopardising cost and
project certainty. Discuss this statement in the context of the case given.
marks
b Paula assigned Daneil a mini project which needs to be completed in months. The budget for
this project is USD with a constant burnt rate the same amount is spent every month
months have passed and Daniel has spent USD. Upon close review, he finds that only
of the work has been completed. Robert, a Cost Portfolio Management expert is being
asked to assist Daniel by calculating and analyzing the following:
i the Schedule Performance Index SPI and Cost Performance index CPI
marks
ii the Estimate at Completion EAC and the Variance at Completion VAC should no measures
be taken to correct any variances identified.
marks
iii. What advice should Robert have for Daneil?
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock