Question: ( Project scheduling ) You are trying to plan a schedule for completing your course projects next semester. You will be given k course projects.

(Project scheduling) You are trying to plan a schedule for completing your course projects next
semester. You will be given k course projects. For each project i, you know the the release time
ri, the length of time li you have to spend on it, and the due date di. You would like to determine
whether you can find an uninterrupted schedule where you are working on exactly one project at a
time from the beginning to the end and satisfying all the deadlines. For simplicity, you can think
of all numbers involved as positive integers. For example, if you have Project 1 released at time 1,
due at time 11, taking 2 time units, Project 2 released at time 3, due at time 9, taking 4 time units,
and Project 3 released at time 2, due at time 7, taking 3 time units, you can have an uninterrupted
schedule as follows: you do Project 3 from 2 to 5, Project 2 from 5 to 9, and Project 1 from 9 to
We formalize this problem as a language as follows: PS={(:k,(r1,l1,d1),dots,(rk,lk,dk):)| all
numbers in the input are positive integers and there exists an uninterrupted schedule
( Project scheduling ) You are trying to plan a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!