Question: Project Selection Dragon Products Company is considering two projects. The projects cash flows are as follows: EXPECTED NET CASH FLOWS YEAR PROJECT A PROJECT B

Project Selection

Dragon Products Company is considering two projects. The projects cash flows are as follows:

EXPECTED NET CASH FLOWS

YEAR

PROJECT A

PROJECT B

0

($9300)

(17,600)

1

2700

3870

2

1930

2450

3

1500

4700

4

2800

4575

5

3200

2450

Discount Rate for both pojects = 7.5%

REQUIRED

  1. Find the Payback Period [PBP] of both projects

  1. What is the Discounted PBP of both projects ?

  1. Calculate the Net Present Value of the two projects and decide which one is better?

  1. What is the profitability index of both products ? What is the function of PI in project selection?

  1. What are the IRR of the projects ? Which of the projects is the best using IRR as a criteria? Why?

  1. Why is sunk cost not considered when deciding about selecting a project? Which cost is considered and why?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!