Question: Project Status: Side (1): Done @ $2,500 Side (2): Done @ $2,500 Side (3): Done @ $3,000 Side (4): 50% @ $1,500 Roof: Not yet

Project Status:

Side (1): Done @ $2,500

Side (2): Done @ $2,500

Side (3): Done @ $3,000

Side (4): 50% @ $1,500

Roof: Not yet started

What is the Earned Value for this project (EV)?

A.

$9,500

B.

$8,750

C.

$8,000

D.

$9,000