Question: Project Status: Side (1): Done @ $2,500 Side (2): Done @ $2,500 Side (3): Done @ $3,000 Side (4): 50% @ $1,500 Roof: Not yet
Project Status:
Side (1): Done @ $2,500
Side (2): Done @ $2,500
Side (3): Done @ $3,000
Side (4): 50% @ $1,500
Roof: Not yet started
What is the Earned Value for this project (EV)?
| A. | $9,500 | |
| B. | $8,750 | |
| C. | $8,000 | |
| D. | $9,000 |