Question: Project Status: Side (1): Done @ $2,500 Side (2): Done @ $2,500 Side (3): Done @ $3,000 Side (4): 50% @ $1,500 Roof: Not yet

Project Status:

Side (1): Done @ $2,500

Side (2): Done @ $2,500

Side (3): Done @ $3,000

Side (4): 50% @ $1,500

Roof: Not yet started

What is the Estimated at Completion (EAC) for this project?

A.

EAC = $15,000

B.

EAC = $17,143

C.

EAC = $18,000

D.

EAC = $16,304