Question: Project Subject The table below shows the defects from XYZ garments factory. Defect type Total defects Skip stitch 2909 Loose thread 43 Misplaced embroidery 300
Project Subject
The table below shows the defects from XYZ garments factory.
| Defect type | Total defects |
| Skip stitch | 2909 |
| Loose thread | 43 |
| Misplaced embroidery | 300 |
| Needle damage | 1287 |
| Broken stitch | 4509 |
| Puckering | 598 |
| Dirty spot | 44 |
| Open seam | 290 |
| Print defect | 598 |
| Button missing | 668 |
| Label missing | 1208 |
Components of the Group Project
-
Analysis of the current scenario
-
Clear usage of tools, included but not limited to, checksheet, pareto analysis
-
-
Identification of the main problem. Choose only one main problem to work with.
-
Brainstorming to find out the root cause of the main problem using fishbone diagram
-
Identification of the root cause of the main problem
-
clear display of hypothetical assumptions / scenario building
-
analysis that is in line with the stated assumptions
-
educated choice of the root cause, consistent with the scenario created
-
-
Action plan to solve the root cause of the main problem
-
Clear list of all required tasks
-
Precedence relationships between the tasks
-
Hypothetical duration mentioned for each task
-
Hypothetical cost mentioned for each task
-
Timeline using Gantt chart
-
Network diagram
-
-
Contingency plan
-
Identification of possible problems that may be faced during the implementation
-
Clear plan to solve/mitigate these possible problems
-
-
Implementation of the action plan
-
Network diagram solution using deterministic times
-
Crashing problem (no daily budget) to show how this project can be expedited
-
Total cost needed for full expedition of the project and total days saved
-