Question: project team has started gathering information necessary to develop a project networkredecessor activities and activity time in days. The results of their meeting are found
project team has started gathering information necessary to develop a project networkredecessor activities and activity time in days. The results of their meeting are found in the llowing table:
tableActivityDescription,Duration,PredecessorI,
Part A Create a network based on the above information. How long will the project take? What is the critical path?
Part B Upon further review the team recognizes that they missed three finishtostart lags. Activity B will only involve days of work but it will take days for the parts to be delivered. Likewise, Activity will take days of work and days for delivery and Activity I needs days of work and days for delivery. Reconfigure the schedule by entering the three finishtostart lags. What impact did these lags have on the original schedule? On the amount of work required to complete the project?
Part C Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finishtostart relationships and that it might be possible to reduce project duration by creating starttostart lags. After much deliberation the team concluded that the following relationships could be converted into starttostart lags:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock