Question: project team has started gathering information necessary to develop a project network - predecessor activities and activity time in days. The results of their meeting
project team has started gathering information necessary to develop a project network
predecessor activities and activity time in days. The results of their meeting are found in the
following table:
Activity Description Duration Predecessor
A
B
C
D
E
F
G
H
I
J
K
L
Part A Create a network based on the above information. How long will the project
take? What is the critical path?
Part B Upon further review the team recognizes that they missed three finishtostart
lags. Activity B will only involve days of work but it will take days for the parts to be
delivered. Likewise, Activity H will take days of work and days for delivery and
Activity I needs days of work and days for delivery. Reconfigure the schedule by
entering the three finishtostart lags. What impact did these lags have on the original
schedule? On the amount of work required to complete the project?
Part C Management is not happy with the schedule and wants the project completed as
soon as possible. Unfortunately, they are not willing to approve additional resources.
One team member pointed out that the network contained only finishtostart
relationships and that it might be possible to reduce project duration by creating start
tostart lags. After much deliberation the team concluded that the following relationships
could be converted into starttostart lags:
Activity B could start days after the start of Activity A
Activity C could start days after the start of Activity A
Activity E could begin day after the start of Activity D
Activity F could start days after the start of Activity E
Activity G could begin days after the start of Activity F
Activity H and Activity I could begin days after Activity G
Kuwait University
Industrial and Management Systems Engineering Department
IMSE: Project Management and Control
Spring Semester
Dr Ayedh Almutairi
Homework Due to
Activity K could begin days after the start of Activity J
Activity L could start days after the start of Activity K
What impact did these lags have on the original schedule Part A How long will the
project take? Is there a change in the critical path? Is there a change in the sensitivity
of the network? Why would management like this solution?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock