Question: project team will receive a bonus if a project is completed earlier per the contract. However, the cost of early completion will be too high

project team will receive a bonus if a project is completed earlier per the contract. However, the cost of early completion will be too high if more resources are added. The risk manager recommends motivating the project team with a slight salary increase instead of contracting more workers for early completion. Which risk response strategy is the risk manager using in this scenario? Enhance Mitigate Transter Escalate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!