Question: project team will receive a bonus if a project is completed earlier per the contract. However, the cost of early completion will be too high
project team will receive a bonus if a project is completed earlier per the contract. However, the cost of early completion will be too high if more resources are added. The risk manager recommends motivating the project team with a slight salary increase instead of contracting more workers for early completion. Which risk response strategy is the risk manager using in this scenario? Enhance Mitigate Transter Escalate
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
