Question: Project Timing 1. Analysis Start: 12/31/22 2. Predevelopment: 12 months 3. Construction: 24 months 4. Lease 1: Commencing 12 months after delivery 5. Lease 2:
Project Timing 1. Analysis Start: 12/31/22 2. Predevelopment: 12 months 3. Construction: 24 months 4. Lease 1: Commencing 12 months after delivery 5. Lease 2: Commencing 24 months after delivery 6. Sale Date: Month 72 or 12/31/28 Project Size: 1. Project GSF: To be determined by applying efficiency below to NRSF 2. Project NRSF: 190,000 SF 3. Project Efficiency: 95% Development Assumptions 1. Land Purchase Price: $80 / GSF to be spent at time zero 2. Soft Costs: $50 /