Question: Project X has the data points below. Task Q has a Cost Variance of Task BCWS BCWP ACWP P 1,000 1.100 1,150 Q 2,000 1,800

Project X has the data points below. Task Q has a Cost Variance of Task BCWS BCWP ACWP P 1,000 1.100 1,150 Q 2,000 1,800 2,100 R 1,000 1,200 1,050 S 2,000 1,900 1,800 O Positive, 300 Negative, 300 Negative, 200 Positive, 2100 O Positive, 200