Question: Project ( X ) is to develop a control system for a new electric vehicle. The main activities of the project are listed

Project \( X \) is to develop a control system for a new electric vehicle. The main activities of the project are listed below. No activity can commence until all its prerequisites are completed.
Table 1- Main Activities of Project \( X \)
\begin{tabular}{|l|l|c|l|}
\hline \multicolumn{1}{|c|}{ Code } & \multicolumn{1}{c|}{ Activity } & Duration (days) & Prerequisite \\
\hline Alpha & High-level requirement. & 1 & None \\
\hline Beta & Detailed requirements of software & 3 & Alpha \\
\hline Gamma & Selection of hardware platform & 2 & Alpha \\
\hline Delta & Programming of modules. & 8 & Beta, Gamma \\
\hline Epsilon & Installation of hardware. & 8 & Gamma \\
\hline Zeta & Hardware Test & 2 & Epsilon \\
\hline Eta & Quality assurance of Programming & 5 & Delta \\
\hline Theta & Integration & 5 & Eta, Zeta \\
\hline Omega & User Test & Theta \\
\hline
\end{tabular}
- Construct an AOA network representation for Project X.
- Construct an AON network representation for Project X .
Project \ ( X \ ) is to develop a control system

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!