Question: Project_Q3 The table below provides the required information for Project Questions Q2, Q3, Q4, and Q5. Task. No Description Predecessor Duration 1 Obtain Authorization 5

Project_Q3 The table below provides the required information for Project Questions Q2, Q3, Q4, and Q5. Task. No Description Predecessor Duration 1 Obtain Authorization 5 2 Hire Scrum Expert 1 25 3 Organize Training 2 10 4 Coordinate Logistics 2 20 5 Announce Training 3 , 4 20 6 Perform Training 5 5 What are the tasks in the critical path