Question: Provide an earned - value analysis to evaluate the progress of a roadway improvement project The original budget is $ 2 0 0 , 0

Provide an earned -value analysis to evaluate the progress of a roadway improvement project The original budget is $ 200,000, and the project is scheduled to be completed in 40 working days. A status report after 15 working days into the project includes the following information : The project is determined to be 25% complete The incurred costs to date are $ 50,000. What is the cost variance ?