Question: Provide an earned value analysis to evaluate the progress of a sewer and water lines project whose original budget is $ 1 4 7 ,

Provide an earned value analysis to evaluate the progress of a sewer and water lines project whose original budget is $147,500. The project is scheduled to be completed in 94 working days. A status report after 10 working days into the project includes the following information:
-Activity 10,100% complete as scheduled, actual cost = $1500 Activity 20,100% complete as scheduled, actual cost = $2200
Activity 30,100% complete as scheduled, actual cost = $4000
-BCWP=7600
-ACWP7700
-BCWS-7600