Question: PROVIDE THE WHOLE EXCEL SOLUTION 9. Find the average completion time, average number of jobs in the system, and the average delay for: a) FCFS

PROVIDE THE WHOLE EXCEL SOLUTION

9. Find the average completion time, average number of jobs in the system, and the average delay for: a) FCFS b) SPT c) EDD dispatching rules. Jobs have been listed in the same sequence as arrival.

FCFS Rule:

Tasks

Time (days)

Due Date

Flow Time

Delay

Results

A

3

10

Avg. Flow Time =

B

7

8

Avg # of jobs =

C

1

12

Avg. Delay =

D

4

7

SPT Rule:

Tasks

Time (days)

Due Date

Flow Time

Delay

Results

Avg. Flow Time =

Avg # of jobs =

Avg. Delay =

EDD Rule:

Tasks

Time (days)

Due Date

Flow Time

Delay

Results

Avg. Flow Time =

Avg # of jobs =

Avg. Delay =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!