FCFS Rule:

Due Date

Time (days)

Due Date

Flow Time

Delay

Results

A

6

21

6

0

Avg. Flow Time =17.25

B

9

18

15

0

Avg # of jobs = 2.76

C

8

15

23

7

Avg. Delay = 2.75

D

2

17

25

4

SPT Rule:

Due Date

Time (days)

Due Date

Flow Time

Delay

Results

Avg. Flow Time =

Avg # of jobs =

Avg. Delay =

EDD Rule:

Due Date

Time (days)

Due Date

Flow Time

Delay

Results

Avg. Flow Time =

Avg # of jobs =

Avg. Delay =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!