Question: PS . 7 4 Bell computer is planning to launch a new high - end server. Nine steps or tasks are required to assemble this
PS Bell computer is planning to launch a new highend server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be units and there are three hour shifts available each day to meet this production quota.
Task Req'd Time in minutes Predecessor
A None
B A
C B
D B
E A
F C D
G F
H E
I G H
What is the total time in minutes to produce one server?
What is the takt time in minutes for this production line? Round your answer to a one decimal place.
What is the theoretical minimum number of workstations required for this production line? Round up your answer to the nearest whole number.
After assigning task A to workstation which task or tasks should you assign to workstation
B
C
D
E
B or E
C and D
Suppose you assign task B to workstation which task or tasks should you then assign to workstation
E and H
C D and F
E
C and D
E by itself or C D and F
Assume you assign tasks C D and F to workstation task E to workstation which task or tasks should you assign to workstation
G and I
G and H
H and I
H
Given your task assignments to workstations, what is the actual number of workstations required?
What is the cycle time in minutes for this production line?
What is the combined idle time in minutes for this production line?
What is the overall efficiency for this production line? Write your answer as a percentage, and display your answer to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock