Question: PT 1 :Project B: What is the project duration for this project? (activity duration is in days) A. 35 B. 25 C. 16 D. 19

PT 1 :Project B: What is the project duration for

PT 1 :Project B: What is the project duration for this project? (activity duration is in days)

A. 35

B. 25

C. 16

D. 19

PT. 2 : Project B: What is/are the critical path(s) for this project?

A. BEGH

B. BDFH

C. BEFH

D. BEGH and CGH

PT. 3 : Project B: If there is a work delay with Activity A, and it now takes 5 days, what is the new slack for D?

A. 3 days

B. 4 days

C. 5 days

D. 6 days

Immediate Predecessor Activity A Activity Duration 4 B 2 6 D A,B 2 9 B DE CE 5 w0I 3 GF 9