Question: PT 1 :Project B: What is the project duration for this project? (activity duration is in days) A. 35 B. 25 C. 16 D. 19

PT 1 :Project B: What is the project duration for this project? (activity duration is in days)
A. 35
B. 25
C. 16
D. 19
PT. 2 : Project B: What is/are the critical path(s) for this project?
A. BEGH
B. BDFH
C. BEFH
D. BEGH and CGH
PT. 3 : Project B: If there is a work delay with Activity A, and it now takes 5 days, what is the new slack for D?
A. 3 days
B. 4 days
C. 5 days
D. 6 days
Immediate Predecessor Activity A Activity Duration 4 B 2 6 D A,B 2 9 B DE CE 5 w0I 3 GF 9Step by Step Solution