Question: Q # 1: (06 Marks) A project has been defined to contain the following list of activities along with their required times for completion. Activity

Q # 1: (06 Marks) A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Duration(weeks) Immediate Predecessors Collect requirements 3 None 2 Analyze processes 2 Analyze data 2 4 Design processes 6 2 Design data 3 3 6 Design screens 2 3. 4 Design reports 4 4. 5 Program 6. 7 Test and Document 7 10 Install 2 8.9 A-Draw activity bar chart B-Draw Staff allocation table (consider the staff name by yourself, hire 6 staff members, 1 for requirement collection, 1 for analysis activities, 1 for design activities, 1 for program, 1 for test & document and 1 for software installation)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts