Question: Q 1 2 - A project is characterized by the following activities, duration, and precedence constraints: A ( 5 weeks ) , no predecessors B

Q12- A project is characterized by the following activities, duration, and precedence constraints:
A (5 weeks), no predecessors
B (2 weeks), A
C (4 weeks), B
D (1 weeks), C & F
E (3 weeks), A
F (3 weeks), E
Which activities are on the critical path?
A) A, B, C, D
B) A, B, C, D, E, F
C) A, E, F, D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!