Question: Q 1 2 - A project is characterized by the following activities, duration, and precedence constraints: A ( 5 weeks ) , no predecessors B
Q A project is characterized by the following activities, duration, and precedence constraints:
A weeks no predecessors
B weeks A
C weeks B
D weeks C & F
E weeks A
F weeks E
Which activities are on the critical path?
A A B C D
B A B C D E F
C A E F D