Question: Q 1 4 From ground level down the soil profile is 2 m sand, 1 0 m clay, then sand to great depth. The entire

Q14 From ground level down the soil profile is 2m sand, 10m clay, then sand to great depth. The entire soil profile is saturated. The clay layer experiences 22mm of settlement in 2 years. Identify how many more years will be required for the consolidation to reach 44mm if the coefficient of consolidation of the layer is 0.001cm2s.
6 years