Question: Q 1 . Consider the following batch sequencing problem: Two chemicals A and B are to be produced. Each chemical requires the use of a

Q1. Consider the following batch sequencing problem:
Two chemicals A and B are to be produced. Each chemical requires the use of a mixer/reactor and a separator unit. The amount of each product made in a batch is the same. The times required to make each chemical along with the value of each chemical are given in the table below.
\table[[Process Unit,Process to make A,Process to make B],[Reactor,6h,8h