Question: Q 1 . Determine the logical steps to reduce the following project to its least - cost scheduling, if the daily indirect cost is

Q1. Determine the logical steps to reduce the following project to its least-cost scheduling, if the daily indirect cost is \(\$ 120\).
\begin{tabular}{|c|c|c|c|c|c|}
\hline & & \multicolumn{2}{|c|}{ Duration } & \multicolumn{2}{c|}{ Cost }\\
\hline Activity & IPA & Normal & Crash & Normal \$ & Crash \$ \\
\hline A & & 5 & 4 & 500 & 600\\
\hline B & A & 7 & 5 & 350 & 500\\
\hline C & A & 8 & 5 & 800 & 920\\
\hline D & A & 11 & 7 & 1,200 & 1,400\\
\hline E & B,C & 6 & 4 & 600 & 700\\
\hline F & C & 4 & 4 & 500 & 500\\
\hline G & D,F & 7 & 5 & 700 & 1,000\\
\hline H & E,F & 6 & 5 & 300 & 420\\
\hline & & & & 4950 & \\
\hline
\end{tabular}
Q 1 . Determine the logical steps to reduce the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!