Question: Q 1 . Draw the current state map for the Value Steam. eltham electromagnetics Ltd produces electromagnetic components and assemblies. One particular line produces assembled

Q1.
Draw the current state map for the Value Steam.
eltham electromagnetics Ltd produces electromagnetic components and
assemblies. One particular line produces assembled microwave emitters for
microwave ovens manufacturer Rapidheat PLC.
Production Processes
The manufacturing line process involves pressing, folding, assembly, testing
and packaging.
The finished assemblies are staged and shipped to the customer each day.
25 coils of stainless-steel sheet are delivered by the supplier, 2 times each
month.
Rapidheats Requirements
2000 components per day. Of which:
1200 are for 240V microwave ovens (European range)
800 are for 120V microwave ovens (American range)
Emitters are to be shipped on trays of 50 units per tray.
The customer orders in multiples of trays.
One daily shipment is sent to the customer by truck.
Rapidheat work 3 shifts per day, 20 working days per month.
Work Time
20 working days per month
2 shifts of 8 hours per day, one (1)/(2) hour meal break, and two 12.5 minute
coffee breaks per shift.
Production Control Department
MRP system
Customer emails demand forecast each week for the next 90 days
Send monthly order for raw materials to supplier by fax
Customer emails daily firm order
Issues weekly schedule to pressing, folding, assembly, testing and
packaging.
Issues daily shipping schedule to despatch.
Process Information
The processes occur in the following sequence and each workpiece passes
through all the processes.
1. Pressing
Cycle Time =1 second, producing 10 components per cycle
Change Over Time =25 minutes
Inventory in front of the process =15 days of raw material
Uptime =90%
1 Operator
2. Folding
Cycle Time =22 seconds
Change Over Time =15 minutes
Inventory in front of the process =4800 European, 3200 American
Uptime =85%
1 Operator
3. Assembly
Cycle Time =56 seconds
Change Over Time =10 minutes
Inventory in front of the process =6000 European, 4000 American
Uptime =100%
2 Operators
4. Testing
Cycle Time =35 seconds
Changeover Time =12 minutes
Inventory in front of process =1800 European, 1200 American
Uptime =100%
1 Operator
5. Packaging
Cycle Time =2 minutes per tray
Changeover Time =30 seconds
Inventory in front of process =3600 European, 2400 American
Uptime =100%
1 Operator
6. Shipping
One shipment per day, typically of 40 trays
Inventory before shipping =240 trays of European assemblies, 160 trays of
American assemblies

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!