Question: Q . 1 . for the table below: a ) Draw the node diagram b ) perform the CPM computations ( ES , EF ,

Q.1. for the table below:
a) Draw the node diagram
b) perform the CPM computations (ES, EF, LS, LF, TF, FF) for the schedule below.
c) What is the independent Floating for activity E?
\table[[Activity,IPA,Duration,Activity,IPA,Duration],[A,-,2,H,D,9],[B,A,7,I,F, G,12],[C,A,10,J,F,5],[D,A,4,K,E, J,5],[E,B,6,L,G, H,6],[F,B, C,5,M,F, H,4],[G,C, D 8,N,I, K, L, M,3,]]