Question: Q 1 . ( W 3 , 1 points ) Please construct the following project activity into a project network and ( 1 . 1

Q1.(W3,1 points) Please construct the following project activity into a project network and
(1.1) Identify the critical path(s) of this project;
(1.2) Specify the slack times for those non-critical activities
Act. ID
Activity Time (in Days)
Immediate Predecessor(s)
A
4
--
B
6
A
C
5
A
D
3
B
E
8
B
F
7
C
G
6
D,E
H
5
F
I
12
G
J
9
G
K
4
H
L
8
I, J
M
7
K, L
N
3
M